Community Sewer System Construction - Harper and Imperial Subdivisions
Dawson Creek, British Columbia
Federal contribution
$534,068
Federal share30%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional District of Peace River
- Construction start
- Jul 21, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2010