Dawson Creek - 102nd Avenue Crossing Replacement
Dawson Creek, British Columbia
Federal contribution
$4.4M
$4,437,049
Federal share80%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Dawson Creek
- Construction start
- Jul 15, 2021(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 2, 2021
- Construction end17 months earlyforecast Mar 31, 2025
Also in Dawson Creek
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59834 in the federal list. How to read these figures.