Jewish Learning Community Centre

Winnipeg, Manitoba

completeRecreationISF
Federal contribution
$320,000
Federal share33%

of $960.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 27, 2009(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Nov 1, 2010