Back to projects

Community Centres Amalgamation

Winnipeg, Manitoba

completeRecreationISF
Federal contribution
$1.5M
$1,500,000
Federal share33%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
201020112012
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Oct 4, 2010(actual)
Construction end
Dec 1, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 15, 2010
  • Construction end3 months earlyforecast Feb 29, 2012