Back to projects

Roadway Repairs to Highway 55

Saint-Boniface, Quebec

completeHighways and RoadsISF
Federal contribution
$2.0M
$1,979,561
Federal share31%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 2, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 14, 2010(actual)
Construction end
Aug 26, 2010(actual)

Against the original forecast

  • Construction end2 months earlyforecast Oct 31, 2010

Also in Saint-Boniface

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36950 in the federal list. How to read these figures.