Repair of interior finishes, building insulation & replacement of a water network.

Saint-Boniface, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$304,000
Federal share80%

of $380.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Dec 21, 2021(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2021
  • Construction end9 months earlyforecast Sep 30, 2022

Also in Saint-Boniface

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60111 in the federal list. How to read these figures.