Back to projects

Wastewater treatment and collection upgrade

Saint-Boniface, Quebec

completeWastewaterCWWF
Federal contribution
$3.1M
$3,105,122
Federal share51%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 27, 2017
2017201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 9, 2017(actual)
Construction end
Oct 13, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2017
  • Construction end18 months earlyforecast Mar 31, 2022

Also in Saint-Boniface