Redevelopment of the Kénogami Town Centre
Federal contribution
$3.6M
$3,585,672
Federal share43%
of $8.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saguenay
- Construction start
- May 12, 2010(actual)
- Construction end
- Feb 11, 2011(actual)
Against the original forecast
- Construction end6 weeks lateforecast Dec 31, 2010
Also in Saguenay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36952 in the federal list. How to read these figures.