Redevelopment of the Kénogami Town Centre

Saguenay, Quebec

completeHighways and RoadsISF
Federal contribution
$3.6M
$3,585,672
Federal share43%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saguenay
Construction start
May 12, 2010(actual)
Construction end
Feb 11, 2011(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Dec 31, 2010