completeCultureISF
Federal contribution
$135,000
Federal share33%

of $405.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 21, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Oct 25, 2009(actual)
Construction end
Jul 30, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Sep 21, 2009
  • Construction end4 weeks lateforecast Jun 30, 2010