New Germany Sewer System - Phase 2
Federal contribution
$458,045
Federal share31%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 23, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Lunenburg
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Mar 25, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 14, 2010
Also in Lunenburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36967 in the federal list. How to read these figures.