Manitoba Childrens Museum
Federal contribution
$1.3M
$1,250,000
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 13, 2009
20102011
Built
Approved 3 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Manitoba Childrens Museum
- Construction start
- Dec 1, 2009(actual)
- Construction end
- Oct 5, 2011(actual)
Also in Winnipeg