Addition of Potable Water piping for Douville sector and repairs to related infrastructure
Federal contribution
$1.6M
$1,579,818
Federal share32%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.4 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Saint-Hyacinthe
- Construction start
- Oct 31, 2013(actual)
- Construction end
- Jan 26, 2016(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2013
- Construction end22 months lateforecast Mar 31, 2014
Also in Saint-Hyacinthe
- Wastewater Treatment Plant Upgrade$24.9M
- Biomethanation and composting project by the City of Saint-Hyacinthe$11.4M
- Upgrading the Filtration Plant$6.9M
- Construction of a recreation/aquatic centre$5.3M
- Railway grading project (grade-separation) in the extension of boulevard Casavant in Saint-Hyacinthe$4.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36977 in the federal list. How to read these figures.