Kirkland Lake Wastewater Improvement
Federal contribution
$16.0M
$15,976,590
Federal share45%
of $35.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 22, 2010
20102012201420162018
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- Corporation of the Town of Kirkland Lake
- Construction start
- Nov 28, 2012(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 30, 2012
- Construction end4 months lateforecast Jun 30, 2017
Also in Kirkland Lake
- Creating a Net Zero Indigenous Community Hub in Northern Ontario$3.0M
- Swastika Sewer System Upgrade / Swastika Water Pollution Control Plant Decommissioning$2.7M
- Equipment Upgrades to Joe Mavrinac Community Complex$2.4M
- Reconstruction of Taylor Avenue and Prospect Avenue$659.1K
- Upgrading of Water, Wastewater and Stormwater Infrastructure on O'Meara Boulevard (Prospect Street to McCamus Avenue)$553.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37224 in the federal list. How to read these figures.