Back to projects

Swastika Sewer System Upgrade / Swastika Water Pollution Control Plant Decommissioning

Kirkland Lake, Ontario

completeWastewaterSCF
Federal contribution
$2.7M
$2,725,133
Federal share33%

of $8.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 7, 2016
2017201920212023
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 28, 2021(actual)
Construction end
Mar 21, 2023(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 5, 2020
  • Construction end9 months lateforecast Jun 30, 2022

Also in Kirkland Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46854 in the federal list. How to read these figures.