Upgrading of Water, Wastewater and Stormwater Infrastructure on O'Meara Boulevard (Prospect Street to McCamus Avenue)

Kirkland Lake, Ontario

completeDrinking WaterCWWF
Federal contribution
$553,503
Federal share41%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2017
20172018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 1, 2017(actual)
Construction end
Aug 30, 2018(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Jul 6, 2018

Also in Kirkland Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51193 in the federal list. How to read these figures.