Back to projects

Resurfacing Route 219 in Saint-Jean-sur-Richelieu

Saint-Jean-sur-Richelieu, Quebec

completeHighways and RoadsISF
Federal contribution
$498,006
Federal share37%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 3, 2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 28, 2010(actual)
Construction end
Dec 6, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Aug 1, 2010
  • Construction end3 months lateforecast Aug 31, 2010

Also in Saint-Jean-sur-Richelieu