Resurfacing Route 219 in Saint-Jean-sur-Richelieu
Saint-Jean-sur-Richelieu, Quebec
Federal contribution
$498,006
Federal share37%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 3, 2010
Built
Approved 4 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Dec 6, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Aug 1, 2010
- Construction end3 months lateforecast Aug 31, 2010