Watermain and Sewer Repairs - Saint-Calixte Street
Federal contribution
$1.3M
$1,290,755
Federal share27%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 2, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Plessisville
- Construction start
- May 17, 2010(actual)
- Construction end
- Dec 17, 2010(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Dec 31, 2010
Also in Plessisville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37255 in the federal list. How to read these figures.