Back to projects

Extension of Méthot Avenue

Plessisville, Quebec

completeHighways and RoadsCC Top Up
Federal contribution
$348,944
Federal share23%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Plessisville
Construction start
Jan 28, 2010(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast Apr 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2011

Also in Plessisville