Extension of Méthot Avenue
Federal contribution
$348,944
Federal share23%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2010
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- City of Plessisville
- Construction start
- Jan 28, 2010(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Apr 1, 2010
- Construction end5 months earlyforecast Mar 31, 2011
Also in Plessisville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39709 in the federal list. How to read these figures.