Renewal of water pipes
Federal contribution
$1.9M
$1,866,113
Federal share50%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
2018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Plessisville
- Construction start
- May 1, 2017(actual)
- Construction end
- May 1, 2018(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end4 weeks lateforecast Mar 31, 2018