Upgrade of Daisy Lake Forest Service Road
Federal contribution
$159,085
Federal share49%
of $327.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedOct 29, 2009
20102011
Built
Approved 7 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Feb 11, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Aug 1, 2010
- Construction end4 weeks lateforecast Jan 15, 2011
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37272 in the federal list. How to read these figures.