Back to projects

Tsawwassen Ferry Terminal

Tsawwassen First Nation, British Columbia

completeMarineISF
Federal contribution
$1.4M
$1,400,000
Federal share50%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Feb 8, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 31, 2009
  • Construction end2 weeks lateforecast Mar 15, 2011

Also in Tsawwassen First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37335 in the federal list. How to read these figures.