Tsawwassen Industrial Lands Site Servicing Project - Phase 1

Tsawwassen First Nation, British Columbia

completeHighways and RoadsISF
Federal contribution
$3.0M
$3,004,081
Federal share33%

of $9.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
First Nations of Tsawwassen
Construction start
Nov 15, 2009(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start7 months earlyforecast Jun 5, 2010
  • Construction end4 weeks earlyforecast Oct 31, 2011

Also in Tsawwassen First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39135 in the federal list. How to read these figures.