Upgrade to Greater Vancouver Water District 52nd St. Water Main

Tsawwassen First Nation, British Columbia

completeDrinking WaterNRP
Federal contribution
$3.7M
$3,702,000
Federal share21%

of $17.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620172018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Tsawwassen First Nation
Construction start
Mar 21, 2016(actual)
Construction end
Apr 4, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Feb 1, 2016
  • Construction end4 months earlyforecast Jul 31, 2018

Also in Tsawwassen First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45843 in the federal list. How to read these figures.