Upgrade to Greater Vancouver Water District 52nd St. Water Main
Tsawwassen First Nation, British Columbia
Federal contribution
$3.7M
$3,702,000
Federal share21%
of $17.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Tsawwassen First Nation
- Construction start
- Mar 21, 2016(actual)
- Construction end
- Apr 4, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Feb 1, 2016
- Construction end4 months earlyforecast Jul 31, 2018
Also in Tsawwassen First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45843 in the federal list. How to read these figures.