Highway 97 Resurfacing
Prince George, British Columbia
Federal contribution
$1.9M
$1,880,585
Federal share50%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- May 26, 2010(actual)
- Construction end
- Jul 7, 2010(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 14, 2010
- Construction end2 weeks lateforecast Jun 21, 2010
Also in Prince George
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37346 in the federal list. How to read these figures.