Highway 97 Resurfacing

Prince George, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.9M
$1,880,585
Federal share50%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 26, 2010(actual)
Construction end
Jul 7, 2010(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 14, 2010
  • Construction end2 weeks lateforecast Jun 21, 2010

Also in Prince George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37346 in the federal list. How to read these figures.