Highway 1 Resurfacing - Blaeberry Bridge East to Golden West Approach
Federal contribution
$1.5M
$1,464,648
Federal share50%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Aug 30, 2010(actual)
- Construction end
- Oct 8, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 30, 2010
Also in Golden
- Kicking Horse Canyon Project Phase 4: West Portal to Yoho Bridge$215.2M
- Kicking Horse Canyon Highway Improvement Project - Phase 2$62.5M
- Trans-Canada Highway 1 - Quartz Creek$49.9M
- Highway 1 Selkirk Mountain Four-Laning$31.5M
- TOWN OF GOLDEN: FLOOD RESILIENCE HIGHWAY 95, KICKING HORSE I & II BRIDGE$28.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37365 in the federal list. How to read these figures.