Route 303 - from Highway 101 to Digby Town Line

Digby, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$1.0M
$1,018,076
Federal share45%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 19, 2010
Built

Approved 3 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Sep 7, 2010(actual)
Construction end
Dec 1, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 15, 2010