Salter Street Access Road
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 23, 2009
ApprovedJan 29, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Vancouver Fraser Port Authority
- Construction start
- Aug 26, 2010(actual)
- Construction end
- Jun 16, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 13, 2010
- Construction end3 months lateforecast Mar 31, 2011
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39056 in the federal list. How to read these figures.