Port Metro Vancouver - South Shore Water and Sewer Improvements

Vancouver, British Columbia

completeMarineISF
Federal contribution
$363,340
Federal share47%

of $775.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 23, 2009
ApprovedJan 29, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 17, 2010(actual)
Construction end
Feb 23, 2011(actual)

Against the original forecast

  • Construction start2 months earlyforecast Oct 30, 2010
  • Construction end5 weeks earlyforecast Mar 31, 2011