Expansion of the Multicultural Helping House Society

Vancouver, British Columbia

completeOtherISF
Federal contribution
$500,000
Federal share32%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 3, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jan 25, 2010(actual)
Construction end
Jan 31, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Oct 1, 2009
  • Construction end4 weeks lateforecast Dec 31, 2010