Science World Restoration
Federal contribution
$10.5M
$10,489,511
Federal share33%
of $31.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 21, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 3 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Science World
- Construction start
- May 24, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 15, 2010
- Construction end2 months earlyforecast Dec 31, 2011
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39060 in the federal list. How to read these figures.