Langley - 202nd Street Park and Ride
Federal contribution
$15.2M
$15,158,638
Federal share50%
of $30.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedNov 19, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Apr 15, 2010(actual)
- Construction end
- Nov 30, 2011(actual)
Against the original forecast
- Construction end13 months earlyforecast Dec 17, 2012
Also in Langley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39102 in the federal list. How to read these figures.