Trans-Canada Highway 1 - High Occupancy Vehicle Lane Extension (216 Street to 264 Street) and Truck Parking Area
Federal contribution
$109.0M
$108,963,550
Federal share50%
of $217.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2019
today
2019202220252028
BuiltForecast
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Mar 31, 2030(forecast)
Against the original forecast
- Construction start3 months earlyforecast Aug 30, 2020