Highway 13 Aldergrove Border Crossing to 8th Avenue

Langley, British Columbia

completeHighways and RoadsMIC
Federal contribution
$10.0M
$10,023,000
Federal share50%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2016
2017201820192020
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Jul 30, 2018(actual)
Construction end
May 31, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2018
  • Construction end7 weeks lateforecast Apr 15, 2020