David Foster Arts Centre
Federal contribution
$1.3M
$1,333,000
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Saanich
- Construction start
- Oct 4, 2010(actual)
- Construction end
- Sep 18, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 15, 2010
- Construction end6 weeks earlyforecast Oct 31, 2011