Abbotsford Airport - Parallel Taxiway and Apron Widening
Federal contribution
$10.0M
$10,000,000
Federal share33%
of $30.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Abbotsford
- Construction start
- Apr 28, 2010(actual)
- Construction end
- Aug 18, 2011(actual)