Mt. Lehman Road 4-Laning: South Fraser Way to Abbotsford Airport Access

Abbotsford, British Columbia

completeHighways and RoadsNRP
Federal contribution
$8.4M
$8,375,000
Federal share49%

of $17.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 19, 2016
2017201820192020
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Sep 4, 2018(actual)
Construction end
Nov 30, 2019(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Sep 30, 2018
  • Construction end6 months earlyforecast May 31, 2020