Mt. Lehman Road 4-Laning: South Fraser Way to Abbotsford Airport Access
Federal contribution
$8.4M
$8,375,000
Federal share49%
of $17.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2016
2017201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of British Columbia
- Construction start
- Sep 4, 2018(actual)
- Construction end
- Nov 30, 2019(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2018
- Construction end6 months earlyforecast May 31, 2020