Highway 11 / Vye Road
Federal contribution
$8.3M
$8,330,000
Federal share35%
of $23.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 15, 2013
ApprovedSep 12, 2016
201420162018202020222024
Built
Approved 3.1 years after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of British Columbia
- Construction start
- Feb 1, 2021(actual)
- Construction end
- Jan 23, 2024(actual)
Also in Abbotsford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44303 in the federal list. How to read these figures.