Glen Drive Development - Vancouver Police Department

Vancouver, British Columbia

completeAdministration, Emergency and Public WorksISF
Federal contribution
$9.7M
$9,708,995
Federal share32%

of $30.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 23, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 3 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Feb 5, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jan 2, 2010

Also in Vancouver