Water Line Renewal

Port McNeill, British Columbia

completeDrinking WaterISF
Federal contribution
$1.4M
$1,400,000
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
201020112012
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Port McNeill
Construction start
Aug 18, 2010(actual)
Construction end
Dec 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 1, 2010
  • Construction end2 months lateforecast Oct 31, 2011