Water Distribution Replacement and Upgrade
Port McNeill, British Columbia
Federal contribution
$963,755
Federal share50%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 30, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Port McNeill
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 10, 2017
- Construction end6 months lateforecast Sep 30, 2018
Also in Port McNeill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47695 in the federal list. How to read these figures.