Water Distribution Replacement and Upgrade

Port McNeill, British Columbia

completeDrinking WaterCWWF
Federal contribution
$963,755
Federal share50%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Port McNeill
Construction start
Sep 5, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 10, 2017
  • Construction end6 months lateforecast Sep 30, 2018

Also in Port McNeill

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47695 in the federal list. How to read these figures.