Port McNeill - Fire Hall Upgrades
Port McNeill, British Columbia
Federal contribution
$271,138
Federal share80%
of $338.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Port McNeill
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Sep 30, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 14, 2021
- Construction end2 months earlyforecast Dec 1, 2024
Also in Port McNeill