Port McNeill - Fire Hall Upgrades

Port McNeill, British Columbia

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$271,138
Federal share80%

of $338.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Port McNeill
Construction start
Aug 2, 2021(actual)
Construction end
Sep 30, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 14, 2021
  • Construction end2 months earlyforecast Dec 1, 2024