Expansion/renovations Carrefour-Ressources
Federal contribution
$23,000
Federal share33%
of $69.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201120122013201420152016
Built
Approved 5.8 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Carrefour-Ressources
- Construction start
- Mar 1, 2015(actual)
- Construction end
- Jun 30, 2015(actual)
Against the original forecast
- Construction start9 months lateforecast May 30, 2014
- Construction end8 months lateforecast Oct 30, 2014
Also in Sainte-Anne-des-Monts
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39190 in the federal list. How to read these figures.