Upgrades to the generator at the Hôpital de Sainte-Anne-des-Monts
Federal contribution
$853,920
Federal share80%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Gaspésie
- Construction start
- May 25, 2021(actual)
- Construction end
- Nov 3, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Mar 15, 2021
- Construction end9 months lateforecast Jan 31, 2023
Also in Sainte-Anne-des-Monts
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59000 in the federal list. How to read these figures.