Water System Upgrades

Sainte-Anne-des-Monts, Quebec

completeDrinking WaterGIS
Federal contribution
$163,664
Federal share40%

of $409.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Sainte-Anne-des-Monts
Construction start
Aug 8, 2023(actual)
Construction end
Oct 7, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 3, 2023
  • Construction end11 months lateforecast Oct 31, 2023

Also in Sainte-Anne-des-Monts

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56450 in the federal list. How to read these figures.