Arterial Streets Rehabilitation - 41st Avenue, Cambie Street to Kingsway
Federal contribution
$829,536
Federal share15%
of $5.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 22, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vancouver
- Construction start
- Jun 30, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 20, 2010
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39361 in the federal list. How to read these figures.