Contracted Distribution Main Replacement - #2 (Kerrisdale and Fraserview)

Vancouver, British Columbia

completeDrinking WaterISF
Federal contribution
$1.1M
$1,119,826
Federal share22%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Sep 7, 2010(actual)
Construction end
Apr 15, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 1, 2010
  • Construction end7 weeks earlyforecast May 31, 2011