Back to projects

Orpheum Theatre Renovations

Vancouver, British Columbia

completeCultureISF
Federal contribution
$852,019
Federal share28%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Jul 13, 2010(actual)
Construction end
Sep 27, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Aug 31, 2011

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39372 in the federal list. How to read these figures.