Stanley Park - Malkin Bowl Performance Centre Upgrade

Vancouver, British Columbia

completeCultureISF
Federal contribution
$355,000
Federal share42%

of $850.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Oct 15, 2010(actual)
Construction end
Oct 17, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Oct 1, 2010
  • Construction end2 weeks earlyforecast Oct 31, 2011

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39377 in the federal list. How to read these figures.