Stanley Park Road Repaving - Sections of Stanley Park Drive and Pipeline Road
Federal contribution
$1.8M
$1,795,866
Federal share50%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 22, 2009
20102011
Built
Approved 2 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vancouver
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Mar 24, 2011(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Apr 1, 2010
- Construction end2 months earlyforecast May 31, 2011
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39379 in the federal list. How to read these figures.