Stanley Park - Sewer Pump Station Upgrades

Vancouver, British Columbia

completeWastewaterISF
Federal contribution
$448,169
Federal share45%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vancouver
Construction start
Oct 20, 2010(actual)
Construction end
Jun 16, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2010
  • Construction end2 weeks lateforecast May 31, 2011